This expansion includes a new 7,500-ton dry fertilizer building equipped with a 24-ton blender and a NTEP certified Auto-Batch blending system. This new building will have the capacity to load 8 semi-trucks per hour. Also included in this project is 1.3 million gallons of liquid fertilizer storage integrated with a crop protection mixing facility and warehouse. This new liquid facility will be equipped with three load bays providing both top and bottom load options with “hot-load” capabilities. Also included will be a 24/7 unattended bay for after-hours availability of nitrogen solution loads with nitrogen stabilizers. Each of these bays can easily fill 6 semi-loads per hour (18 semi-loads total/hour for the facility). In addition to these, the expansion will feature 72,000 gallons of bulk crop protection product storage contained in this facility and ample mini-bulk and package good storage that will provide tremendous flexibility and capacity.